NEVLEC apologises after fresh unplanned outages hit Nevis during generator overhaul
A second generating unit developed a fault while the main generator was already out for maintenance, forcing more power cuts across the island on Friday.

CHARLESTOWN, Nevis. The Nevis Electricity Company (NEVLEC) has apologised to customers after unplanned power cuts spread across the island on Friday, when a second generator developed a technical fault while its main unit was already offline.
The state-owned utility said the unexpected problem further reduced its generating capacity and forced it to widen load management to keep the grid stable. It did not identify which unit had failed or say how much capacity had been lost.
Overhaul already straining supply
The outages came during a planned top-end overhaul of Generator No. 12 at the Prospect Power Station, which NEVLEC announced on 9 November. At the time the company said the work was expected to be completed by 15 November, followed by checks before the unit returned to service.
That notice said rolling cuts would be needed at peak times and that a schedule of affected areas and times would follow in a separate announcement. In its latest statement, issued through the Nevis Island Administration on Monday, the company did not say whether the overhaul had finished on time or when normal supply would return.
NEVLEC said its technical team was working to restore normal operations safely and as quickly as possible, and expressed regret for the disruption to households and businesses.
The company has also launched a WhatsApp channel for real-time updates on outages and restoration work, and urged customers to follow it.
The interruptions add to pressure on the Nevis Island Administration over the cost and reliability of electricity. Its cabinet said last month it was exploring possible relief measures as fuel costs rise, while civil works on the island's geothermal project continue ahead of the arrival of its drilling rig.